Flexible building for Temporary Factory

Prize: 25.000 €

Status: completed

Background

Grupo Pacadar is the leading firm in Spain in the design, manufacturing and assembly of precast, pre-stressed reinforced concrete structures. 

The internationalization of Pacadar is one of their main strategic objectives. Once a construction project in a specific country is awarded, Pacadar develops the investment plan for a precast concrete manufacturing plant in said country, located as close to the work site as possible.

Their ability to rapidly install factories overseas means they are able to start manufacturing prefabricated structures in a short space of time. The plants recently built in Panama, México or Riad serve as an example of their investment in prefabricated plants abroad. 

The challenge

Pacadar is currently developing a new phase of internationalization using precast concrete temporary factories. And the need is to become more flexible and cost-effective to change the location of their factories, i.e. reducing the time and costs of building assembly and disassembly, along with the transportation to a new worksite. The building is used 5 times, for 5 contracts and you might consider a lifecycle of 10 years.

Current factory dimensions are 11m high x 22m x 150m and its purpose is essentially to protect the manufacturing equipment and personnel from sun and rain. A factory typically contains a rolling bridge crane for moving precast concrete over a floor made of concrete slab.

Today lifecycle costs for a single factory include factory building material acquisition (that is reused 5 times) and operational costs (transportation to site location, assembly and disassembly):

Cost element

Units

Actual unit cost

Actual costs

Foundation

22 x 150 m = 3.300 m2 x 5 times

16 €/m2

264.200 €

Building Material

22 x 150 m = 3.300 m2 x 1 time (if reusable)

90 €/m2

297.000 €

Assembly

22 x 150 m = 3.300 m2 x 5 times

17.4 €/m2

287.100 €

Disassembly

22 x 150 m = 3.300 m2 x 5 times

17.4 €/m2

287.100 €

Transportation

280 T per building, 12 containers x 5 times = 60 containers

5.000 €/40ft 24T Open Top container

300.000 €

Operational cost

-

-

0 €

LIFE CYCLE COST (5 TIMES / 10 YEARS)

1.435.200 €

Actual concrete cost (including excavation, steel, concrete and formwork) for the foundation is 280 €/m3.

Actual building material (Structural steel for beams and pillars) cost is 1.06€/Kg (excludes transport and assembly).

Actual assembly and disassembly unit costs in previous table have been calculated according to the following data:

  • Labor: 600 €/day (Team of 3 workers, 10 h/day and average labor cost 20 €/man-h)
  • Crane: 550 €/day
  • Man-lift: 120 €/day

What the client is looking for

Pacadar is looking for a solution to increase flexibility (less assembly and disassembly time) while reducing the mobile factory lifecycle costs (5 times use during a 10 years timeframe):

  • Reduce building acquisition cost with a different technology or material
  • Reduce time / effort (e.g. man-hours) to assemble / disassemble the factory
  • Reduce transportation costs with lower weight / volume and easy handling

Any solution should comply with the following technical specification:

Warehouse model

Characteristic

Value

Width

22 m

Length

150 m

Free height under beam

11,75 m

Live Load (kN/m2)

0.80

Wind load (kN/m2)

0.89

Seismic coefficient

0,194

Locations – Codes (the building must to accomplish both rules in order to be installed in America or Europe)

Europe - Eurocode and

America - AISC

Other solutions have been studied like inflatable tents, portable hangars or buildings made of containers, pre-fabricated arcs, etc. but never found a more efficient solution. In fact, the less time to erect the factory, the more expensive are the acquisition costs. Other solutions are cheaper but the total cost for assemble and disassemble are higher.

As an example inflatable vessels used by the army, with canvas pipes and balances, about 35-40m long, enable a very fast assembly (about 1 week) and lower cost (about 5 €/m2) but inflating maintenance cost makes the solution not attractive (of 1 € / m2 and month).

We will share additional information as required.

This is a 3 rounds tournament with the following expected submissions: 

First round

  • Brief description of the propose solution, including sketches, pictures or drawings.
  • High-level acquisition costs and estimated assembly duration.
  • Feasibility evidence.

Second round

  • Detailed solution specification including materials, dimensions, etc.
  • Components specifications and potential suppliers.
  • Detailed lifecycle costs calculation (acquisition and operational costs). 

If required, additional information will be provided during the course of this round.

Third round

  • Clarifications on the proposed solution (if existing solution)
  • Preliminary technical project brief (if new development)

Evaluation criteria

Submissions will be assessed according to the following criteria:

  • Technical feasibility of proposed solution
  • Higher flexibility (assembly, disassembly)
  • Lower lifecycle costs (expected 20-40%)

Lifecycle costs should be provided according to the following template: 

Cost element

Units

Solution unit cost

Solution costs

Building Material

22 x 150 m = 3.300 m2 x 1 time (if reusable)

 

 

Assembly

22 x 150 m = 3.300 m2 x 5 times

 

 

Disassembly

22 x 150 m = 3.300 m2 x 5 times

 

 

Transportation

 

5.000 €/40ft 24T Open Top container

 

Operational

 

0,12 Kw/h (if energy is required)

 

Other

 

 

 

LIFE CYCLE COST (5 TIMES / 10 YEARS)

 

In case the building acquisition cost is higher than actual solution then an annual financial cost rate of 5% should be considered in the economic calculation (only for the cost difference in the acquisition of the building material).

Timeline

This is a 3 round tournament with the following timings

  • 1st round – 6 weeks+ 2 week for evaluation
  • 2nd round – 3 weeks + 2 week for evaluation
  • 3rd round – 2 weeks + 2 week for evaluation
How to join
  • 1. Sign up and complete your profile
  • We recommend you to sign up with your Linkedin or Google credentials. Otherwise, you will be asked to validate your account email.
  • Register as a representative of your company or as an individual.
  • Share your skills, so we can invite you to challenges or projects that may be of your interest.
  • 2. Join a challenge or apply to a project
  • Once logged in, make sure you go to the ecosystem where the challenge or project has been posted.
  • If you haven't done this before, it may be necessary to complete your profile in order to proceed.
  • Don’t forget to mark the deadline in your calendar to send your submission.
  • 3. Prepare and send your solution or project proposal
  • Check out the challenge or project attachments with additional information.
  • Make your submission concise. A 3-5 pages pdf document might be sufficient, although you can send additional documents such as drawings, calculations or specifications.

    Good Luck!